Works on the Campaspe and Bulls Siphons, in northern Victoria, have been completed on time and under budget.
Subscribe now for unlimited access to all our agricultural news
across the nation
or signup to continue reading
The siphons were restored and replaced, during Goulburn-Murray Water’s annual winter irrigation shutdown, between May and August.
The two works sites are five kilometres apart, on one of GMW’s main carriers, the Waranga Western Channel.
Lead Project Manager Linc Wellington said the $2.5 million work on Bulls Siphon, which was designed and constructed ‘in-house’ by G-MW, was delivered on time and about $200,000 under budget.
The project involved removing the old deteriorated structure and replacing it with a new four-barrel, three-metre diameter reinforced concrete structure.
“The added bonus of carrying out these works ourselves was that we had control of project timeframes and schedules,” Mr Wellington said.
“Some minor out-of-channel works are still happening so customers may see our staff in the area for a couple of weeks yet.”
At Campaspe Siphon, the three existing barrels have been re-lined with fibre-reinforced concrete.
The barrels allow water from the Waranga Western Channel to pass under the Campaspe River without interference.
“The newly-relined siphon barrels are now in use,” Mr Wellington said.
“We’re happy to say this project was also completed on time and within our $3.7 million budget.”
“This project was originally intended to be carried out over two winter periods but we were able to make some project innovations and find a way to complete the works this winter.
“This has saved us a lot of time and costs for remobilisation.”
G-MW managing director Pat Lennon said the works will ensure the historic assets continue to provide service to both Rochester and the Loddon Valley Irrigation Districts well into the future.
“Campaspe Siphon was first built in the early 1900s and was nearing the end of its serviceable life, which is why these works needed to happen,” Mr Lennon said.
“ Ongoing patch works have taken place in previous years but this will be the first time since construction that significant upgrades have taken place.
Adopting an innovative re-lining approach for Campaspe Siphon, utilising fibre-reinforced concrete, represented a large cost-saving for customers.
“The replacement cost of this infrastructure was estimated to be in the vicinity of $12 million, so coming in under $4 million was a great result,” he said.
Mr Lennon said Bulls Siphon had similarly experienced significant deterioration and was at the end of its life prior to this winter’s refurbishment.